Opportunity Information: Apply for FR RRD 13 009
Apply for FR RRD 13 009
- The DOT/Federal Railroad Administration in the transportation sector is offering a public funding opportunity titled "FY13 HYBRID ROAD LOCOMOTIVE FOR ENERGY SAVINGS AND REDUCED EMISSIONS" and is now available to receive applicants.
- Interested and eligible applicants and submit their applications by referencing the CFDA number(s): 20.313 Railroad Research and Development.
- This funding opportunity was created on Jun 10, 2013 and posted on Jun 10, 2013.
- Applicants must submit their applications by Jun 28, 2013 No Explanation. (Agency may still review applications by suitable applicants for the remaining/unused allocated funding in 2026.)
- Each selected applicant is eligible to receive up to $250,000.00 in funding.
- Eligible applicants include: Others (see text field entitled Additional Information on Eligibility for clarification).
- Only Norfolk Southern Corporation is eligible to apply for this grant.
[Watch] Creating a grant proposal using the step-by-step wizard inside the applicant portal:
Opportunity Summary:
The FY13 HYBRID ROAD LOCOMOTIVE FOR ENERGY SAVINGS AND REDUCED EMISSIONS opportunity (Funding Opportunity Number FR RRD 13 009) was a discretionary grant issued by the U.S. Department of Transportation, Federal Railroad Administration (FRA), under the Railroad Research and Development program (CFDA 20.313). The purpose of the grant was to support applied research aimed at improving locomotive energy efficiency and reducing emissions by advancing hybrid locomotive technology that combines a diesel powertrain with an onboard energy storage system (ESS).
The work described in the announcement focused specifically on Norfolk Southern Corporation carrying out extensive testing, modeling, and early-stage integration of a lithium nickel manganese cobalt (Li NMC) battery system packaged by Corvus Energy. The technical objective was to evaluate how a high-voltage battery string could be incorporated into locomotive traction power architecture and how different operating strategies might deliver measurable fuel savings and emissions reductions in real-world duty cycles. To do that, the project planned both switching-cycle testing (yard and low-speed operations with frequent starts and stops) and line-of-road test protocols (mainline operation with different power demands and sustained running), since hybrid benefits and control strategies can vary widely between these operating regimes.
A central element of the scope was testing a 104 kWh battery string made up of sixteen Corvus Energy AT6500 48V Li NMC modules wired in series. Wiring these modules in series was intended to produce an approximately 800 V DC bus, a voltage level commonly needed for locomotive traction systems. This 800 V DC bus requirement is important because modern locomotive traction and power electronics operate at high voltages to efficiently deliver large amounts of power to traction motors; the project was therefore oriented toward validating that this battery configuration could meet locomotive electrical integration needs, at least at the level of initial integration and performance characterization.
Administratively, the grant was posted on June 10, 2013, with an original and current closing date of June 28, 2013, and an archive date of July 28, 2013. The award ceiling was $250,000 and the award floor was $0, and the opportunity required cost sharing or matching. Eligibility was narrowly limited: only Norfolk Southern Corporation was permitted to apply, making this effectively a targeted, single-applicant research award rather than a broadly competed solicitation. For access issues, the announcement directed users to the GrantSolutions Help Desk via phone or email during standard weekday business hours.
FAQs: FY13 Hybrid Road Locomotive for Energy Savings and Reduced Emissions (FR RRD 13 009)
What is the name of this grant opportunity?
The opportunity is titled "FY13 HYBRID ROAD LOCOMOTIVE FOR ENERGY SAVINGS AND REDUCED EMISSIONS."
What is the Funding Opportunity Number (FON)?
The Funding Opportunity Number is FR RRD 13 009.
Which federal agency issued this grant?
This was a discretionary grant issued by the U.S. Department of Transportation (USDOT), Federal Railroad Administration (FRA).
What program did the grant fall under?
The grant was issued under the FRA Railroad Research and Development program.
What is the CFDA number associated with this opportunity?
The CFDA number listed for this opportunity is 20.313.
What was the purpose of the grant?
The purpose was to support applied research to improve locomotive energy efficiency and reduce emissions by advancing hybrid locomotive technology that combines a diesel powertrain with an onboard energy storage system (ESS).
What type of work was supported (research vs. deployment)?
Based on the description, the work was applied research focused on testing, modeling, and early-stage integration activities rather than broad commercial deployment.
Who was the intended applicant for this opportunity?
Eligibility was narrowly limited: only Norfolk Southern Corporation was permitted to apply.
Was this a competitive solicitation open to multiple applicants?
No. The eligibility restriction to a single entity (Norfolk Southern Corporation) indicates it was a targeted, single-applicant research award rather than a broadly competed solicitation.
Was cost sharing or matching required?
Yes. The opportunity required cost sharing or matching.
What was the maximum award amount (award ceiling)?
The award ceiling was $250,000.
What was the minimum award amount (award floor)?
The award floor was $0.
What organization and activity did the announcement focus on?
The announcement focused specifically on Norfolk Southern Corporation conducting extensive testing, modeling, and early-stage integration of a lithium nickel manganese cobalt (Li NMC) battery system packaged by Corvus Energy.
What battery chemistry was planned for evaluation?
The project planned to evaluate a lithium nickel manganese cobalt (Li NMC) battery system.
Which company packaged the battery system referenced in the scope?
The battery system was packaged by Corvus Energy.
What was the main technical objective of the project?
The technical objective was to evaluate how a high-voltage battery string could be incorporated into locomotive traction power architecture and how different operating strategies might produce measurable fuel savings and emissions reductions in real-world duty cycles.
What is meant by "hybrid locomotive technology" in this opportunity?
In this opportunity, hybrid locomotive technology refers to combining a diesel powertrain with an onboard energy storage system (ESS), enabling different control and operating strategies intended to save fuel and reduce emissions.
What specific battery string configuration was a central element of the testing scope?
A central element was testing a 104 kWh battery string made up of sixteen Corvus Energy AT6500 48V Li NMC modules wired in series.
How many battery modules were included in the battery string?
The battery string consisted of sixteen modules.
What model and voltage rating were the battery modules?
The modules were Corvus Energy AT6500 48V Li NMC modules.
What was the planned total energy capacity of the battery string?
The planned battery string energy capacity was 104 kWh.
Why were the modules wired in series?
They were wired in series to produce an approximately 800 V DC bus, which aligns with voltage levels commonly needed for locomotive traction systems.
What DC bus voltage level was the project aiming to achieve?
The configuration was intended to produce an approximately 800 V DC bus.
Why is an 800 V DC bus relevant to locomotives?
The description notes that modern locomotive traction and power electronics operate at high voltages to efficiently deliver large amounts of power to traction motors, so validating an approximately 800 V DC bus configuration supported the project’s initial integration and performance characterization goals.
What kinds of operating regimes were included in the testing plan?
The project planned both switching-cycle testing and line-of-road test protocols.
What is switching-cycle testing in the context described?
Switching-cycle testing was described as yard and low-speed operations with frequent starts and stops.
What is line-of-road testing in the context described?
Line-of-road testing was described as mainline operation with different power demands and sustained running.
Why did the project plan to test both switching and line-of-road duty cycles?
The scope notes that hybrid benefits and control strategies can vary widely between these operating regimes, so both were included to evaluate performance across different real-world duty cycles.
What kinds of project activities were mentioned?
The announcement described extensive testing, modeling, and early-stage integration of the battery system into locomotive traction power architecture, along with evaluation of operating strategies for fuel savings and emissions reductions.
When was the opportunity posted?
The grant was posted on June 10, 2013.
What was the application closing date?
The original and current closing date was June 28, 2013.
Was the closing date changed from the original date?
No. The information states the original and current closing date were both June 28, 2013.
When was the opportunity archived?
The archive date was July 28, 2013.
Where were applicants directed for help with access issues?
For access issues, users were directed to the GrantSolutions Help Desk via phone or email during standard weekday business hours.
What kinds of outcomes was the project trying to demonstrate?
The project aimed to evaluate and support strategies that could deliver measurable fuel savings and emissions reductions in real-world locomotive duty cycles by advancing hybrid locomotive technology.
Browse more opportunities from the same category: Transportation
Next opportunity: OJJDP FY 13 Youth with Sexual Behavior Problems Program
Previous opportunity: Americas Historical and Cultural Organizations
USGrants.org Applicant Portal:
Are you interested in learning about about how to apply for this government funding opportunity? You can create a free applicant account and receive instant access to our applicant portal that many business owners like you have benefited from.
Apply for FR RRD 13 009
[Watch] how do funding administrators access proposals?
Applicants also applied for:
Applicants who have applied for this opportunity (FR RRD 13 009) also looked into and applied for these:
| Funding Opportunity |
|---|
| FY 2014 MCSAP Border Enforcement Grant Notice of Funding Availability Apply for FM BEG 14 001 Funding Number: FM BEG 14 001 Agency: DOT/Federal Motor Carrier Safety Administration Category: Transportation Funding Amount: $25,000,000 |
| Access Road Project Apply for F13AS00198 Funding Number: F13AS00198 Agency: Fish and Wildlife Service Category: Transportation Funding Amount: Case Dependent |
| FY 2014 MCSAP New Entrant Notice of Funding Availability Apply for FM MNE 14 001 Funding Number: FM MNE 14 001 Agency: DOT/Federal Motor Carrier Safety Administration Category: Transportation Funding Amount: $9,000,000 |
| FY 2014 MCSAP High Priority Notice of Funding Availability Apply for FM MHP 14 001 Funding Number: FM MHP 14 001 Agency: DOT/Federal Motor Carrier Safety Administration Category: Transportation Funding Amount: $1,000,000 |
| Small Community Air Service Development Program Apply for DOT OST 2013 0120 Funding Number: DOT OST 2013 0120 Agency: DOT Office of Aviation Analysis Category: Transportation Funding Amount: $11,500,000 |
| FY13 OLI Highway Railroad Grade Crossing Safety Education and Enforcement Program Apply for FR OLS 13 001 Funding Number: FR OLS 13 001 Agency: DOT/Federal Railroad Administration Category: Transportation Funding Amount: $1,015,000 |
| BUS EFFICIENCY ENHANCEMENTS RESEARCH AND DEMONSTRATIONS Apply for FTA 2013 003 TRI Funding Number: FTA 2013 003 TRI Agency: DOT/Federal Transit Administration Category: Transportation Funding Amount: $3,000,000 |
| Grants For Transportation Of Veterans In Highly Rural Areas Apply for VA HRTG 2014 Funding Number: VA HRTG 2014 Agency: Chief Business Office Category: Transportation Funding Amount: $50,000 |
| Design and Construction of Continuously Reinforced Concrete for Long Life Pavement Performance Apply for DTFH61 13 RA 00016 Funding Number: DTFH61 13 RA 00016 Agency: DOT Federal Highway Administration Category: Transportation Funding Amount: $500,000 |
| FY13 Law Enforcement Liaison Program to Prevent Grade Crossing and Trespass Incidents Apply for FR LEL 13 001 Funding Number: FR LEL 13 001 Agency: DOT/Federal Railroad Administration Category: Transportation Funding Amount: $37,500 |
| Air Quality and Congestion Mitigation Measure Outcomes Assessment Study Apply for DTFH61 13 RA 00018 Funding Number: DTFH61 13 RA 00018 Agency: DOT Federal Highway Administration Category: Transportation Funding Amount: $1,250,000 |
| DOT PHMSA 2014 Hazardous Liquid Base Grant Apply for DOT PH PHP 14 HL Funding Number: DOT PH PHP 14 HL Agency: Pipeline Hazardous Material Safety Administration Category: Transportation Funding Amount: Case Dependent |
| DOT PHMSA 2014 Natural Gas Base Grant Apply for DOT PH PHP 14 NG Funding Number: DOT PH PHP 14 NG Agency: Pipeline Hazardous Material Safety Administration Category: Transportation Funding Amount: Case Dependent |
| Education and Enforcement in Pedestrian Focus Cities Apply for DTNH22 13 R 00728 Funding Number: DTNH22 13 R 00728 Agency: DOT/National Highway Traffic Safety Administration Category: Transportation Funding Amount: $2,000,000 |
| 2013 Work Zone Safety Grants Apply for DTFH61 13 RA 00019 Funding Number: DTFH61 13 RA 00019 Agency: DOT Federal Highway Administration Category: Transportation Funding Amount: $3,000,000 |
| Technology Transfer of Best Practices for Concrete and Concrete Pavements Apply for DTFH61 13 RA 00017 Funding Number: DTFH61 13 RA 00017 Agency: DOT Federal Highway Administration Category: Transportation Funding Amount: $600,000 |
| Advancement of Innovative Asphalt Technologies Apply for DTFH61 13 RA 00015 Funding Number: DTFH61 13 RA 00015 Agency: DOT Federal Highway Administration Category: Transportation Funding Amount: $2,000,000 |
| FY10 Rail Spur Extension, Greater Ouachita Parish, LA Apply for FR LRI 10 026 Funding Number: FR LRI 10 026 Agency: DOT/Federal Railroad Administration Category: Transportation Funding Amount: $2,000,000 |
| Tribal Transportation Program Safety Funds Apply for FHWA 2013 0012 Funding Number: FHWA 2013 0012 Agency: DOT Federal Highway Administration Category: Transportation Funding Amount: $8,600,000 |
| National Work Zone Safety Information Clearinghouse Apply for DTFH61 13 RA 00020 Funding Number: DTFH61 13 RA 00020 Agency: DOT Federal Highway Administration Category: Transportation Funding Amount: $1,840,000 |
Grant application guides and resources
It is always free to apply for government grants. However the process may be very complex depending on the funding opportunity you are applying for. Let us help you!
Apply for Grants

Premium leads for funding administrators, grant writers, and loan issuers
Thousands of people visit our website for their funding needs every day. When a user creates a grant proposal and files for submission, we pass the information on to funding administrators, grant writers, and government loan issuers.
If you manage government grant programs, provide grant writing services, or issue personal or government loans, we can help you reach your audience.
Subscribe to Leads
Request more information:
Would you like to learn more about this funding opportunity, similar opportunities to "FR RRD 13 009", eligibility, application service, and/or application tips? Submit an inquiry below:
Don't forget to subscribe to our grant alerts mailing list to receive weekly alerts on new and updated grant funding opportunities like this one in your email.