Opportunity summary
The project scope is heavily engineering-driven and is structured to move from field data collection to engineered design and then into procurement and construction-phase support. The selected partner is expected to document site conditions and produce bid-ready plans rather than simply offering conceptual guidance. A key deliverable is a set of stamped (sealed) engineering design drawings suitable for inclusion in a formal bid package. These drawings must reflect current topographic elevations and include detailed, typical water control structure design elements so the refuge can confidently purchase and install the replacement structures in accordance with professional standards and Service expectations.
Work is divided into three defined tasks. Task 1 covers fieldwork and preliminary engineering: documenting site topography and existing features associated with the current water control structures, then producing suitable construction plans along with a preliminary design and cost estimate to guide decision-making and ensure the project can meet its objective within budget and logistical constraints. Task 2 advances the effort into final design and procurement planning: delivering a final set of sealed engineering plans suitable for purchase and installation, soliciting bids for the needed water control structure materials, reviewing the bids received, and forwarding bid information to U.S. Fish and Wildlife Service (FWS) staff for approval. Task 3 shifts into implementation support: purchasing the water control structure materials and providing construction inspection during installation, helping ensure the work is built according to the approved plans and that any issues encountered in the field are handled with appropriate engineering oversight.
Funding for the opportunity is fixed at an estimated total of $167,000, with the award floor and ceiling both listed as $167,000, and the agency anticipates making one award. No cost sharing or matching is required. The opportunity is categorized under Natural Resources and is associated with CFDA 15.637 (Migratory Bird Joint Ventures). A wide range of applicant types are listed as eligible, including state and local governments (county, city/township, special district), nonprofits (including both 501(c)(3) and certain non-501(c)(3) entities), small businesses, and for-profit organizations other than small businesses.
The announcement was posted February 24, 2011, created February 28, 2011, and had an application closing date of March 3, 2011, with the listing archived April 2, 2011. The funding opportunity number is NWRS R2 21640 FY11 01, and the sponsoring agency is listed as Region 2. For assistance accessing the full announcement or for additional details, the point of contact provided is Renee Robichaud, Assistant Refuge Supervisor, at 505-248-6480 or reneerobichaud@fws.gov.
Frequently asked questions
What is the Sequoyah NWR Water Control Structure Replacement Project?
This is a discretionary cooperative agreement opportunity focused on restoring and improving wetland management infrastructure at Sequoyah National Wildlife Refuge near Vian, Oklahoma. The work centers on surveying and engineering support needed to replace 27 aging and deteriorated water control structures that are limiting the refuge's ability to manage water levels across existing wetland units.
What is the main purpose of this grant opportunity?
The core purpose is to regain reliable control of wetland hydrology by replacing 27 water control structures that are no longer in good condition. Reliable water-level control supports habitat conditions and broader natural resource goals tied to the National Wildlife Refuge System.
Where will the project take place?
The project is located at Sequoyah National Wildlife Refuge near Vian, Oklahoma.
How many water control structures are included in the replacement effort?
The project is intended to support the replacement of 27 existing water control structures.
What type of work is expected under this cooperative agreement?
The scope is engineering-driven and is structured to move from field data collection to engineered design and then into procurement and construction-phase support. The selected partner is expected to document site conditions and produce bid-ready plans, not just conceptual recommendations.
What are the major phases or tasks described in the announcement?
The work is divided into three defined tasks: (1) fieldwork and preliminary engineering, (2) final design and procurement planning, and (3) purchasing materials and providing construction inspection during installation.
What is included in Task 1?
Task 1 covers fieldwork and preliminary engineering, including documenting site topography and existing features associated with the current water control structures, producing suitable construction plans, and providing a preliminary design and cost estimate.
What is included in Task 2?
Task 2 advances the work into final design and procurement planning. It includes delivering a final set of sealed engineering plans suitable for purchase and installation, soliciting bids for the needed water control structure materials, reviewing bids received, and forwarding bid information to U.S. Fish and Wildlife Service (FWS) staff for approval.
What is included in Task 3?
Task 3 covers implementation support, including purchasing the water control structure materials and providing construction inspection during installation to help ensure the work is built according to the approved plans and that field issues are handled with appropriate engineering oversight.
What is a key required deliverable?
A key deliverable is a set of stamped (sealed) engineering design drawings suitable for inclusion in a formal bid package. The drawings must reflect current topographic elevations and include detailed, typical water control structure design elements.
Are conceptual designs sufficient for this project?
No. The scope emphasizes producing bid-ready, professionally prepared plans that the refuge can use to purchase and install replacement structures according to professional standards and Service expectations.
What is the total funding amount for this opportunity?
The estimated total funding is $167,000. The award floor and ceiling are both listed as $167,000.
How many awards does the agency expect to make?
The agency anticipates making one award.
Is cost sharing or matching required?
No. The announcement states that no cost sharing or matching is required.
What funding category is this opportunity listed under?
The opportunity is categorized under Natural Resources.
What CFDA number is associated with this opportunity?
The opportunity is associated with CFDA 15.637 (Migratory Bird Joint Ventures).
Who is eligible to apply based on the listing?
The listing includes a wide range of eligible applicant types, including state governments, local governments (county, city/township, special district), nonprofits (including 501(c)(3) and certain non-501(c)(3) entities), small businesses, and for-profit organizations other than small businesses.
What is the funding opportunity number?
The funding opportunity number is NWRS R2 21640 FY11 01.
Which agency or region is sponsoring the opportunity?
The sponsoring agency is listed as Region 2.
When was the opportunity posted and when did it close?
The announcement was posted on February 24, 2011. The application closing date is listed as March 3, 2011.
When was the opportunity created and when was it archived?
The listing was created on February 28, 2011, and it was archived on April 2, 2011.
Who is the point of contact for questions or help accessing the full announcement?
The point of contact is Renee Robichaud, Assistant Refuge Supervisor.
How can the point of contact be reached?
Phone: 505-248-6480. Email: reneerobichaud@fws.gov.
What does the project aim to improve at the refuge?
By replacing deteriorated structures, the refuge aims to restore reliable control of wetland water levels (wetland hydrology), which is central to maintaining habitat conditions and supporting broader natural resource goals.
What does "bid-ready" mean in the context of this project?
In this announcement, bid-ready refers to producing sealed engineering plans and related documentation suitable for inclusion in a formal bid package, allowing the refuge to solicit bids and purchase/install the replacement structures with confidence.
Does the scope include procurement-related activities?
Yes. Task 2 includes soliciting and reviewing bids for materials and forwarding bid information to FWS staff for approval, and Task 3 includes purchasing the water control structure materials.
Does the scope include construction oversight?
Yes. Task 3 includes providing construction inspection during installation to help ensure construction matches the approved plans and is supported by appropriate engineering oversight.
Questions about this opportunity?
Contact USGrants.org for help with this listing or similar funding opportunities.
Contact USGrants.orgRelated funding listings
Applicants who have applied for this opportunity (NWRS R2 21640 FY11 01) also looked into and applied for these: